DFD #16C3B
The project involves repaving the entire length of Eagle Heights Drive on the UW Madison campus. The roadway is approximately 2,500 lineal feet long and is owned by the UW-Madison. The repaving will involve full depth removal of the asphalt and replacement. Concrete curb is assumed at 10% replacement. Some amount of Excavation Below Subgrade (EBS) is expected in order to replace poor subgrade soils.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $468,300 |
Construction | $360,000 |
Design | $28,700 |
Mgt. | $16,600 |
Contingency | $54,000 |
Equipment | – |
Other Fees | $9,000 |
Sources | |
Gifts & Grants | $468,300 |
Timeline
A/E Selection | 05/2016 |
35% Design Report | 03/2016 – 10/2016 |
Construction Documents | 06/2016 – 12/2016 |
Bid Date | 03/2017 |
Construction | 06/2017 – 09/2017 |
Substantial Completion | 09/2017 |
Occupancy | 09/2017 |
Key Stakeholders
Occupants | N/A |
User Reps | Evan Quilling |
UW PM | Matt Collins |
DFD PM | Jake Ehmke |
A/E | OTIE |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Tri-County Paving |
Plumbing | N/A |
Mechanical | N/A |
Fire Protection | N/A |
Electrical | N/A |