DFD #16F2E
This project will plan, design and construct one general assignment, collaborative learning classroom, creating it from two existing general assignment classrooms on the first and second floors of Ingraham Hall.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $822,000 |
Construction | $534,000 |
Design | $65,700 |
Mgt. | $23,500 |
Contingency | $52,500 |
Equipment | $146,000 |
Other Fees | – |
Funding Sources: | |
Gifts & Grants | $412,000 |
GFSB | $412,000 |
Timeline
A/E Selection | 08/2017 – 11/2017 |
35% Design Report | 10/2017 |
Construction Documents | 01/2018 |
Bid Date | 05/2018 |
Construction | 06/2018 – 11/2018 |
Substantial Completion | 11/2018 |
Occupancy | 12/2018 |
Key Stakeholders
Occupants | SMO General Assignment |
User Reps | N/A |
UW PM | Peter Bloechl-Anderson |
DFD PM | Russ Van Gilder |
A/E | AroEberle |
Design Arch. | Michael Eberle |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 2,603 |
ASF | N/A |
Efficiency | N/A |
Construction $/GSF | $205 |
Total Project $/GSF | $316 |