DFD #15A1Y
Replacement of 167,150 SF of Hypalon roof membranes and replace with new fully adhered 60-mil single-ply EPDM membrane system and new metal flashing, refinishing ventilators and rehabilitating lightning protection system.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $2,612,700 |
Construction | $2,152,000 |
Design | $150,700 |
Mgt. | $94,700 |
Contingency | $215,300 |
Equipment | – |
Other Fees | – |
Funding Sources: | |
PR Funds | $2,612,700 |
Timeline
A/E Selection | 02/2015 |
35% Design Report | 05/2015 – 11/2015 |
Construction Documents | 01/2016 – 03/2016 |
Bid Date | 06/2016 |
Construction | 09/2016 – 06/2017 |
Substantial Completion | 06/2017 |
Occupancy | 06/2017 |
Key Stakeholders
Occupants | Athletic Department |
User Reps | Barry Fox |
UW PM | Matt Collins |
DFD PM | Owen Landsverk |
A/E | Facilities Engineering, Inc. |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Quality Roofing, Inc. |
Plumbing | N/A |
Mechanical | N/A |
Fire Protection | N/A |
Electrical | N/A |