DFD #15A1Y
Replacement of 167,150 SF of Hypalon roof membranes and replace with new fully adhered 60-mil single-ply EPDM membrane system and new metal flashing, refinishing ventilators and rehabilitating lightning protection system.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total | $2,612,700 |
| Construction | $2,152,000 |
| Design | $150,700 |
| Mgt. | $94,700 |
| Contingency | $215,300 |
| Equipment | – |
| Other Fees | – |
| Funding Sources: | |
| PR Funds | $2,612,700 |
Timeline
| A/E Selection | 02/2015 |
| 35% Design Report | 05/2015 – 11/2015 |
| Construction Documents | 01/2016 – 03/2016 |
| Bid Date | 06/2016 |
| Construction | 09/2016 – 06/2017 |
| Substantial Completion | 06/2017 |
| Occupancy | 06/2017 |
Key Stakeholders
| Occupants | Athletic Department |
| User Reps | Barry Fox |
| UW PM | Matt Collins |
| DFD PM | Owen Landsverk |
| A/E | Facilities Engineering, Inc. |
| Design Arch. | N/A |
| Landscape Arch. | N/A |
| Structural Engr. | N/A |
| General Contractor | Quality Roofing, Inc. |
| Plumbing | N/A |
| Mechanical | N/A |
| Fire Protection | N/A |
| Electrical | N/A |