MSN #0038-1601
This project resurfaces the indoor tennis courts and expands the outdoor courts from six to eight on the north side of the stadium adjacent to the existing outdoor courts. It also improves spectator experience by adding a sound system, LED court lighting that meets NCAA standards, individual scoreboards for the center six courts, and spectator seating for about 600 people.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $2,136,120 |
Construction | $1,729,445 |
Design | $174,920 |
Mgt. | $67,200 |
Contingency | $164,555 |
Equipment | – |
Other Fees | – |
Funding Sources: | |
Gifts & Grants | $2,136,120 |
Timeline
Indoor | |
A/E Selection | 01/2017 |
Construction Documents | 02/2017 – 05/2017 |
Bid Date | 05/2017 |
Construction | 08/2017 – 09/2017 |
Occupancy | 09/2017 |
Outdoor | |
35% Design Report | 10/2017 – 01/2018 |
Construction Documents | 02/2018 – 04/2018 |
Bid Date | 04/2018 |
Construction | 5/2018 – 08/2018 |
Substantial Completion | 09/2018 |
Occupancy | 09/2018 |
Key Stakeholders
Occupants | UW Athletics |
User Reps | Barry Fox |
UW PM | Matt Collins |
DFD PM | N/A |
A/E | Edge Consulting |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
GC Indoor | Armstrong |
GC Outdoor | TBD |
Plumbing | N/A |
Mechanical | N/A |
Fire Protection | N/A |
Electrical | N/A |