MSN #0039-1701
This project renovates approximately 6,000 ASF/9,000 GSF of the second floor of the WARF Office Building to meet the needs of the School of Medicine and Public Health’s Department of Biostatistics and Medical Informatics. The fourth floor of the building is anticipated to be similarly renovated as a separate project in the future.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $1,422,000 |
Construction | $945,000 |
Design | $177,000 |
Mgt. | $38,000 |
Contingency | $142,000 |
Equipment | $120,000 |
Other Fees | – |
Funding Sources: | |
Gifts & Grants | $1,422,000 |
Timeline
A/E Selection | 09/2017 |
Design | 10/2017-04/2018 |
Construction Documents | 05/2018 |
Bid Date | 06/2018 |
Construction-Floor 2 | 07/2018-11/2018 |
Sub. Completion Flr 2 | 12/2018 |
Occupancy-Floor 2 | 01/2019 |
Final Completion | 02/2019 |
Key Stakeholders
Occupants | SMPH |
User Rep | Mark Wells |
UW PM | Rex Loker |
DFD PM | Tom Bittner |
A/E | Flad Architects |
Design Arch. | Flad Architects |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | TBD |
Plumbing | IMEG |
Mechanical | IMEG |
Fire Protection | IMEG |
Electrical | IMEG |
Area Data
GSF | 9,000 |
ASF | 6,000 |
Efficiency | 66.67% |
Construction $/GSF | $105.00 |
Total Project $/GSF | $158.00 |