This replacement project demolishes the 125,118 ASF / 191,254 GSF Southeast Recreation Facility (SERF) and constructs a 181,830 ASF / 250,800 GSF facility which is a 31% expansion. It will include all the required utility improvements and house expanded spaces such as functional fitness areas, a nine-basketball court gymnasium, an indoor walking and jogging track, and several multi-purpose rooms. A 50-meter competition pool and separate diving well will be shared between Recreational Sports and the Division of Intercollegiate Athletics.
This is an accordion element with a series of buttons that open and close related content panels.
BUDGET
| Total Soft Costs | $23,631,000 |
| Total Construction Costs | $72,910,000 |
| Total Project Costs | $96,541,000 |
| Funding Sources: | |
| PRSB | $53,872,600 |
| Gift/Grant | $42,080,000 |
| Cash | $588,400 |
TIMELINE
| A/E Selection | 09/2015 |
| Design Report | 02/2017 |
| Bid Date | 08/2008 |
| Start Construction | 10/2017 |
| Substantial Completion | 01/2020 |
KEY STAKEHOLDERS
| Occupants | Rec Sports |
| User Reps | John Horn |
| UW PM | Ann Hayes |
| DFDM PM | Wendy von Below |
| A/E | Workshop Architects, Inc. |
| Design Arch. | HOK |
| Landscape Arch. | Ken Saiki Design |
| Structural Engr. | GRAEF-USA Inc. |
| General Contractor | Miron Construction |
| Plumbing | Hooper Corp. |
| Mechanical | NAMI |
| Fire Protection | JF Ahern |
| Electrical | Staff Electric |
AREA DATA
| GSF | 248,300 |
| ASF | 170,800 |
| Efficiency | 68.79% |
| Construction $/GSF | $294 |
| Total Project $/GSF | $361 |
Our vision for the new “SERF” is a facility that will allow us to inspire our students, members, and the community to play hard, get fit, and live well.