DFD #14B2R
The $800,000 project consists of renovating 3 floors, approximately 4,700 GSF of space, at the Dairy Cattle Center for the Dairy Science Department.
The scope includes updating plumbing, mechanical, and electrical systems. The women’s locker room in the basement will be renovated to serve as a women’s bathroom. The ground floor lobby will be remodeled as an educational outreach space. A women’s locker room and new showers will be created on the second floor. The existing second floor classroom will receive new flooring, a 6-ft stainless steel sink, and a countertop. The existing second floor bathroom and the men’s bathroom and locker room in the basement will be updated to meet ADA requirements.
This project was completed in July 2017.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $800,000 |
Construction | $625,000 |
Design | $50,000 |
Mgt. | $27,500 |
Contingency | $62,500 |
Equipment | $0 |
Other Fees | $35,000 |
Sources | |
GSRB | $800,000 |
Timeline
A/E Selection | 05/2014 |
Planning | 07/2014 – 11/2014 |
Programming | 12/2014 – 02/2015 |
10% Concept Report | 03/2015 – 04/2015 |
35% Design Report | 05/2015 – 10/2015 |
Construction Documents | 10/2015 – 02/2016 |
Bid Date | 02/2016 |
Construction | 06/2016 – 06/2017 |
Substantial Completion | 07/2017 |
Occupancy | 07/2017 |
Key Stakeholders
Occupants | CALS |
User Reps | Doug Sabatke |
UW PM | Ann Hayes |
DFD PM | Russ Van Gilder |
A/E | BWZ Architects |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Sonag Company Inc. |
Plumbing | Hooper Corp. |
Mechanical | General Heating & Air |
Fire Protection | Hooper Corp. |
Electrical | Forward Electrical |
Area Data
GSF | 4,686 |
ASF | 3,414 |
Efficiency | 72.86% |
Construction $/GSF | $133 |
Total Project $/GSF | $171 |