DFD #15J2K
This pre-design study establishes conceptual design options for the Lot 62 parking ramp. The intent of this study is to develop and evaluate concept options to provide campus with a parking facility that includes a minimum of 600 parking stalls (including ADA-compliant parking), motorcycle/moped parking, and bicycle parking. Concepts were analyzed and developed that expand on the initial work conducted to develop concepts for the expansion of the School of Veterinary Medicine (SVM
This is an accordion element with a series of buttons that open and close related content panels.
BUDGET
Feasibility Study Total | $74,750 |
Future Project: | |
Total | $16,800,000 |
Construction | $13,450,000 |
Design | $1,070,000 |
Mgt. | $590,000 |
Contingency | $1,340,000 |
Equipment | $300,000 |
Other Fees | $50,000 |
TIMELINE
A/E Selection | 04/2016 |
Draft Report | 11/2016 |
Final Report-Study | 05/2017 |
KEY STAKEHOLDERS
Occupants | UW Transportation |
User Reps | UW Transportation |
UW PM | Matt Collins |
DFD PM | Tim Luttrell |
A/E | Kimley-Horn |
Design Arch. | NA |
Landscape Arch. | NA |
Structural Engr. | NA |
AREA DATA
GSF | 190,200 |
ASF | 180,690 |
Efficiency | TBD |
Construction $/GSF | TBD |
Total Project $/GSF | TBD |