MSN #0102-1706
This project includes renovationg 3,800 ASF / 4,000 GSF of the fourth floor of 445 Henry Mall for the Office of Strategic Consulting (OSC). OSC is currenlty housed in another building on campus and the new space will create a contiguous area for their recently merged divisions. In addition to the office space, a shared common area will be created that includes a breakroom and a conference room.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $810,000 |
Construction | $550,000 |
Design | $60,000 |
Contingency | $55,000 |
Equipment | $125,000 |
Other Fees | $20,000 |
Funding Sources: | |
Gifts & Grants | $810,000 |
Timeline
A/E Selection | 03/2018 |
25% Design Report | 04/2018 – 5/1/2018 |
Construction Documents | 07/2018 |
Bid Date | 07/2018-09/2018 |
Construction | 10/2018 |
Substantial Completion | 02/2019 |
Occupancy | 03/2019 |
Key Stakeholders
Occupants | Office of Stategic Consulting |
User Reps | Jenny Faust |
UW PM | Bo Muwahid |
A/E | Aro Eberle |
Design Arch. | TBD |
Landscape Arch. | TBD |
Structural Engr. | TBD |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 4,000 |
ASF | 3,800 |
Efficiency | 95.00% |
Construction $/GSF | $136 |