DFD #19C1Y
This project will provide pre-design, and design services to renovate and maintain multiple athletic facilities to address safety, customer satisfaction, energy efficiency, and enhance the experience of patrons.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $296,000 |
| Total Construction Costs | $2,699,000 |
| Total Project Costs | $2,995,000 |
| Funding Sources: | |
| Cash | $2,995,000 |
Timeline
| A/E Selection | 06/2019 |
| Design Report | 10/2019 |
| Bid Date | 02/2020 |
| Start Project | 04/2020 |
| Substantial Completion | 12/2021 |
Key Stakeholders
| Occupants | UW Athletics |
| User Reps | Barry Fox |
| UW PM | Brandon Braithwaite |
| DFDM PM | Tim Luttrell |
| A/E | Berners-Schober Associates |
| Structural Engr. | N/A |
| General Contractor | TBD |
| Plumbing | TBD |
| Mechanical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
Area Data
| GSF | N/A |
| ASF | N/A |
| Efficiency | N/A |
| Construction $/GSF | N/A |
| Total Project $/GSF | N/A |