MSN #0050-1614
This project will re-purpose an existing lecture hall into office space for campus administration. The 4,000 GSF / 2,600 ASF project is completely gift-funded and will include a new reception area to support the Office of the Chancellor and a suite of private offices and workstations. The historic integrity of the original space will remain intact.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $642,000 |
| Total Construction Costs | $1,258,000 |
| Total Project Costs | $1,900,000 |
| Funding Sources: | |
| Gift/Grant | $1,900,000 |
Timeline
| A/E Selection | 03/2014 |
| Design Report | 05/2018 |
| Bid Date | 09/2019 |
| Start Construction | 11/2019 |
| Substantial Completion | 05/2020 |
Key Stakeholders
| Occupants | UW Relations |
| User Reps | Jordan Hanson |
| UW PM | Megan McBride |
| A/E | Boer Architects |
| Design Arch. | Boer Architects |
| Structural Engr. | Michael Corrigan |
| General Contractor | TBD |
| Plumbing | TBD |
| Mechanical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
Area Data
| GSF | 4,000 |
| ASF | 2,600 |
| Efficiency | 65.00% |
| Construction $/GSF | $390 |
| Total Project $/GSF | $475 |