MSN #0050-1614
This project will re-purpose an existing lecture hall into office space for campus administration. The 4,000 GSF / 2,600 ASF project is completely gift-funded and will include a new reception area to support the Office of the Chancellor and a suite of private offices and workstations. The historic integrity of the original space will remain intact.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $642,000 |
Total Construction Costs | $1,258,000 |
Total Project Costs | $1,900,000 |
Funding Sources: | |
Gift/Grant | $1,900,000 |
Timeline
A/E Selection | 03/2014 |
Design Report | 05/2018 |
Bid Date | 09/2019 |
Start Construction | 11/2019 |
Substantial Completion | 05/2020 |
Key Stakeholders
Occupants | UW Relations |
User Reps | Jordan Hanson |
UW PM | Megan McBride |
A/E | Boer Architects |
Design Arch. | Boer Architects |
Structural Engr. | Michael Corrigan |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 4,000 |
ASF | 2,600 |
Efficiency | 65.00% |
Construction $/GSF | $390 |
Total Project $/GSF | $475 |