DFD #18H1W
The project will update the systems, finishes, and furnishings while preserving, restoring, and augmenting the historical integrity and beauty of the historic lecture hall in Bascom Hall. In addition, this project will provide an additional active learning classroom on campus in the 70-99 seat range by renovating three existing, underutilized spaces to create one large classroom in Van Vleck Hall.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $546,173 |
Total Construction Costs | $841,785 |
Total Project Costs | $1,387,957 |
Funding Sources: | |
Gift/Grant | $1,462,000 |
Timeline
A/E Selection | 09/2018 |
Design Report | 04/2019 |
Bid Date | 08/2019 |
Start Construction | 11/2019 |
Substantial Completion | 05/2020 |
Key Stakeholders
Occupants | Campus |
User Reps | Abe Schrump |
UW PM | Megan McBride |
DFDM PM | Matt Dapp |
A/E | Aro Eberle |
Structural Engr. | N/A |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 5,872 |
ASF | 5,872 |
Efficiency | 100.00% |
Construction $/GSF | $141 |
Total Project $/GSF | $235 |