MSN #0084-1802
This project will create a laboratory space for two cryo-electron microscopes. The laboratory space will be constructed to BSL-2 standards and will have areas for various sample prep.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $341,000 |
| Total Construction Costs | $1,909,000 |
| Total Project Costs | $2,250,000 |
| Funding Sources: | |
| Gift/Grant | $2,250,000 |
Timeline
| A/E Selection | 10/2018 |
| Design Report | 12/2018 |
| Bid Date | 05/2019 |
| Start Construction | 07/2019 |
| Substantial Completion | 12/2019 |
Key Stakeholders
| Occupants | Biochemistry |
| User Reps | Brian Fox / Liz Wright |
| UW PM | Mike Zimmerman |
| DFDM PM | N/A |
| A/E | Aro Eberle |
| Structural Engr. | OTIE |
| General Contractor | Findorff |
| Plumbing | Hooper |
| Mechanical | Belonger |
| Fire Protection | Ahern |
| Electrical | Staff |
Area Data
| GSF | 1,562 |
| ASF | 1,274 |
| Efficiency | 81.00% |
| Construction $/GSF | $1,033 |
| Total Project $/GSF | $1,125 |