MSN #0205-1704
This project will add an addition to the Biochemistry Laboratories loading dock and raise the adjacent elevation roughly 30″ to eliminate flooding that occurs frequently during heavy rain events. The existing storm sewers will also be increased in size at the Biochemistry Building as well as near the Bock Labs loading dock.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $200,000 |
Total Construction Costs | $1,450,000 |
Total Project Costs | $1,650,000 |
Funding Sources: | |
Gifts & Grants | $1,650,000 |
Timeline
A/E Selection | 09/2017 |
Design Report | 09/2018 |
Bid Date | 05/2019 |
Start Construction | 06/2019 |
Substantial Completion | 12/2019 |
Key Stakeholders
Occupants | Biochemistry |
User Reps | Brian Fox / Doug Sabatke |
UW PM | Bo Muwahid |
DFDM PM | TBD |
A/E | Delta 3 Engineering |
Design Arch. | Delta 3 Engineering |
Structural Engr. | Delta 3 Engineering |
General Contractor | Findorff |
Area Data
GSF | N/A |
ASF | N/A |
Efficiency | N/A |
Construction $/GSF | N/A |
Total Project $/GSF | N/A |