MSN #0055-1703
This project takes existing student office space and converts it into two laboratories for a new faculty member. The labs will implement a dedicated air handler as the two new labs will have strict temperature and relative humidity controls.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $715,000 |
Construction | $378,000 |
Design | $68,000 |
Contingency | $255,000 |
Equipment | |
Other Fees | $14,000 |
Funding Sources: | |
Gifts & Grants | $715,000 |
Timeline
A/E Selection | 08/2017 |
25% Design Report | 09/2017 – 11/2017 |
Construction Documents | 12/2017 – 03/2018 |
Bid Date | 04/2018 – 05/2018 |
Construction | 6/1/2018 – 10/2018 |
Substantial Completion | 10/2018 |
Occupancy | 11/2018 |
Key Stakeholders
Occupants | Physics Department |
User Reps | Aimee Lefkow |
UW PM | Bo Muwahid |
DFD PM | N/A |
A/E | Assemblage Architects |
Design Arch. | Assemblage Architects |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Advanced Building Corp. |
Plumbing | Hooper Corp. |
Mechanical | H&H Indsutries |
Fire Protection | N/A |
Electrical | Universal Power Systems |
Area Data
GSF | 1,300 |
ASF | 1,200 |
Efficiency | 92.31% |
Construction $/GSF | $402 |
Total Project $/GSF | $550 |