MSN #0047-1803
This project seeks to remodel two rooms on the fourth floor of the Chemistry building into a lab for three Class IV lasers. The lab needs to be a highly controlled space with tight temperature controls that lower airborne particulate counts for the laser microscopy work.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $76,724 |
| Total Construction Costs | $541,022 |
| Total Project Costs | $617,746 |
| Funding Sources: | |
| Gifts & Grants | $617,000 |
Timeline
| A/E Selection | 11/2018 |
| Design Report | 04/2019 |
| Bid Date | 09/2019 |
| Start Construction | 12/2019 |
| Substantial Completion | 05/2020 |
Key Stakeholders
| Occupants | Chemistry Department |
| User Reps | Jeff Nielson |
| UW PM | Megan McBride |
| DFDM PM | N/A |
| A/E | Aro Eberle |
| Structural Engr. | Aro Eberle |
| General Contractor | TBD |
| Plumbing | TBD |
| Mechanical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
Area Data
| GSF | 675 |
| ASF | 550 |
| Efficiency | 81.48% |
| Construction $/GSF | $606 |
| Total Project $/GSF | $761 |