MSN #0047-1803
This project seeks to remodel two rooms on the fourth floor of the Chemistry building into a lab for three Class IV lasers. The lab needs to be a highly controlled space with tight temperature controls that lower airborne particulate counts for the laser microscopy work.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $76,724 |
Total Construction Costs | $541,022 |
Total Project Costs | $617,746 |
Funding Sources: | |
Gifts & Grants | $617,000 |
Timeline
A/E Selection | 11/2018 |
Design Report | 04/2019 |
Bid Date | 09/2019 |
Start Construction | 12/2019 |
Substantial Completion | 05/2020 |
Key Stakeholders
Occupants | Chemistry Department |
User Reps | Jeff Nielson |
UW PM | Megan McBride |
DFDM PM | N/A |
A/E | Aro Eberle |
Structural Engr. | Aro Eberle |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 675 |
ASF | 550 |
Efficiency | 81.48% |
Construction $/GSF | $606 |
Total Project $/GSF | $761 |