DFD #16H2U
The existing UW Arboretum Curtis Storm Water Detention Pond must be rehabilitated to repair a failed flume and failing outlet structure, restoring the pond’s ability to control peak stormwater runoff flow rates and remove accumulated stormwater sediment. This project is funded in part through an Intergovernmental Agreement between the University of Wisconsin, the City of Madison, and the Town of Madison dated February 2009.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $165,000 |
Total Construction Costs | $959,000 |
Total Project Costs | $1,124,000 |
Funding Sources: | |
GFSB | $550,450 |
PR Cash | $203,590 |
Others | $1,354,960 |
Timeline
A/E Selection | 11/2016 |
Design Report | 10/2017 |
Bid Date | 11/2019 |
Start Construction | 12/2019 |
Project Close-Out | 09/2020 |
Key Stakeholders
Occupants | UW Arboretum |
User Reps | N/A |
UW PM | Brandon Braithwaite |
DFDM PM | Jim Schaefer |
A/E | Strand Associates, Inc. |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | N/A |
ASF | N/A |
Efficiency | N/A |
Construction $/GSF | N/A |
Total Project $/GSF | N/A |