MSN #0175-1701
The intent of this project is to remodel and expand the home locker room, coaches’ locker room, and sport medicine areas. This includes approximately 1700 s.f. of existing space to remodel with the possible addition of 500 s.f. of new building. The remodeled and new spaces will have new graphics to complement the UW Athletics brand. The new furniture and finishes will reflect the use and character of the sport.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $972,000 |
Construction | $735,000 |
Design | $110,000 |
UW MSN Fee | $28,000 |
Contingency | $74,000 |
Equipment | $25,000 |
Other Fees | – |
Funding Sources: | |
Gifts & Grants | $972,000 |
Timeline
A/E Selection | 08/2017 |
25% Design Report | 09/2017 – 04/2018 |
Construction Documents | 04/2018 – 07/2018 |
Bid Date | 07/2018 |
Construction | 09/2018 – 01/2019 |
Substantial Completion | 01/2019 |
Occupancy | 03/2019 |
Key Stakeholders
Occupants | UW Athletics |
User Reps | Barry Fox |
UW PM | Matt Collins |
A/E | Berners-Schober |
Design Arch. | Berners-Schober |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 2,200 |
ASF | 1,900 |
Efficiency | 86.36% |
Construction $/GSF | $334 |
Total Project $/GSF | $442 |