This project will demolish the Gymnasium/Natatorium (Gym/Nat) facility that no longer adequately supports the space needs of Recreational Sports and construct a replacement facility on the same site. The project provides space for a wellness center, a new gift-funded ice arena, basketball courts, indoor track, fitness space and racquetball courts as well as enhanced activity areas that will generate additional revenue.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $10,000,000 |
| Total Construction Costs | $85,000,000 |
| Total Project Costs | $95,000,000 |
| Funding Sources: | |
| PRSB | $60,600,000 |
| Gift/Grant | $34,400,000 |
Timeline
| A/E Selection | 04/2019 |
| Design Report | 04/2020 |
| Bid Date | 12/2020 |
| Start Construction | 02/2021 |
| Substantial Completion | 12/2022 |
Key Stakeholders
| Occupants | Recreational Sports |
| User Reps | John Horn |
| UW PM | Bo Muwahid |
| DFDM PM | Wendy von Below |
| A/E | Kahler Slater |
| Design Arch. | HOK |
| Landscape Arch. | GRAEF |
| Structural Engr. | OTIE |
| MEP Engr. | Mead+Hunt/ IMEG |
| General Contractor | TBD |
| Plumbing | TBD |
| Mechanical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
Area Data
| GSF | 262,108 |
| ASF | 170,200 |
| Efficiency | 64.94% |
| Construction $/GSF | N/A |
| Total Project $/GSF | N/A |