This music performance facility project for the Mead Witter School of Music is a significant component of the University’s East Campus Development Plan. The project will provide a 650-seat concert hall, a 330-seat recital hall, and a large rehearsal room.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $10,502,400 |
| Total Construction Costs | $45,297,600 |
| Total Project Costs | $55,800,000 |
| Funding Sources: | |
| Gift/Grant | $55,800,000 |
Timeline
| A/E Selection | 11/2010 |
| Design Report | 03/2015 |
| Bid Date | 12/2016 |
| Start Construction | 02/2017 |
| Substantial Completion | 09/2019 |
Key Stakeholders
| Occupants | School of Music |
| User Reps | Susan Cook |
| UW PM | Bo Muwahid |
| DFDM PM | N/A |
| A/E | Strang, Inc. |
| Design Arch. | Holzman Moss Bottino |
| Architecture, LLP | |
| Landscape Arch. | Ken Saiki Design |
| Structural Engr. | R.A. Smith |
| General Contractor | JP Cullen |
| Plumbing | Hooper Corp. |
| Mechanical | General Heating |
| Fire Protection | USA Fire Protection |
| Electrical | Nickles |
Area Data
| GSF | 74,840 |
| ASF | 55,250 |
| Efficiency | 73.82% |
| Construction $/GSF | $645 |
| Total Project $/GSF | $746 |