This music performance facility project for the Mead Witter School of Music is a significant component of the University’s East Campus Development Plan. The project will provide a 650-seat concert hall, a 330-seat recital hall, and a large rehearsal room.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $10,502,400 |
Total Construction Costs | $45,297,600 |
Total Project Costs | $55,800,000 |
Funding Sources: | |
Gift/Grant | $55,800,000 |
Timeline
A/E Selection | 11/2010 |
Design Report | 03/2015 |
Bid Date | 12/2016 |
Start Construction | 02/2017 |
Substantial Completion | 09/2019 |
Key Stakeholders
Occupants | School of Music |
User Reps | Susan Cook |
UW PM | Bo Muwahid |
DFDM PM | N/A |
A/E | Strang, Inc. |
Design Arch. | Holzman Moss Bottino |
Architecture, LLP | |
Landscape Arch. | Ken Saiki Design |
Structural Engr. | R.A. Smith |
General Contractor | JP Cullen |
Plumbing | Hooper Corp. |
Mechanical | General Heating |
Fire Protection | USA Fire Protection |
Electrical | Nickles |
Area Data
GSF | 74,840 |
ASF | 55,250 |
Efficiency | 73.82% |
Construction $/GSF | $645 |
Total Project $/GSF | $746 |