MSN# 0018-1803
This project will bring College Library restrooms up to current code requirements by providing toilet and lavatory counts that reflect current occupancy. The roughly 1500 SF of restrooms on the first three floors of Helen C. White Hall were constructed in 1968 and are no longer adequate for faculty, staff, students, and patrons that visit the library.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $249,500 |
Total Construction Costs | $860,500 |
Total Project Costs | $1,110,000 |
Funding Sources: | |
Gifts & Grants | $1,110,000 |
Timeline
A/E Selection | 03/2018 |
Design Report | 09/2018 |
Bid Date | 01/2019 |
Construction | 02/2019 |
Substantial Completion | 09/2019 |
Key Stakeholders
Occupants | General Library System |
User Reps | Carrie Kruse |
UW PM | Megan McBride |
DFDM PM | N/A |
A/E | HGA |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Advanced Building Corp. |
Plumbing | HJ Pertzborn |
Mechanical | Universal Power & Systems |
Fire Protection | N/A |
Electrical | 1901, Inc. |
Area Data
GSF | 3,750 |
ASF | 3,000 |
Efficiency | 80.00% |
Construction $/GSF | $297 |
Total Project $/GSF | $296 |