The project will design and renovate approximately 140,000 GSF / 80,000 ASF of floors 1, 2, 3 and 4 of HSLC to enhance the Academic Affair’s teaching, administrative, and public space. All of the spaces will be designed as one project with a cohesive aesthetic.
The project also includes space for a quiet student study lounge and renovation of strategic office spaces including the Multicultural Affairs and the Native American Center for Health Professions along with conference room upgrades.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $6,141,955 |
Total Construction Costs | $9,883,309 |
Total Project Costs | $16,025,264 |
Funding Sources: | |
Gifts & Grants | $16,025,264 |
Timeline
A/E Selection | 10/2016 |
Design Report | 12/2016 |
Bid Date | 04/2017 |
Start Construction | 06/2017 |
Substantial Completion | 08/2018 |
Occupancy | 10/2018 |
Key Stakeholders
Occupants | SMPH |
User Reps | Mark Wells |
UW PM | Peter Bloechl-Anderson |
A/E | OPN/SLAM |
Design Arch. | OPN/SLAM |
Landscape Arch. | N/A |
Structural Engr. | OPN/SLAM |
General Contractor | JP Cullen |
Plumbing | Hooper Corp. |
Mechanical | J.F. Ahern |
Fire Protection | H.J. Pertzborn |
Electrical | Westphal |
Area Data
GSF | 140,000 |
ASF | 80,000 |
Efficiency | 57.14% |
Construction $/GSF | $73 |
Total Project $/GSF | $114 |