The work consists of replacing steam pits 17/11 and 120 LF of concrete box conduit with an accessible utility tunnel from steam pit 17/11 to the north terminating at a location suitable for connection to the Chemistry Building Addition and Renovation project currently under construction. The utility tunnel work includes replacement of the 18-inch HPS, 20-inch LPS, 8-inch PCR, and 3-inch CA piping, insulation, and supporting system. The 18-inch HPS will be increased in size to 20-inch HPS.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $1,071,000 |
Total Construction Costs | $3,740,000 |
Total Project Costs | $4,811,000 |
Funding Sources: | |
GFSB | $3,319,600 |
PRSB | $1,491,400 |
Timeline
A/E Selection | 12/2016 |
Design Report | N/A |
Bid Date | 06/2018 |
Start Construction | 07/2019 |
Substantial Completion | 05/2019 |
Project Close-Out | 08/2019 |
Key Stakeholders
Occupants | FP&M Physical Plant |
UW PM | Jeff Pollei |
DFDM PM | Michael Hanson |
A/E | Ring & DuChateau, LLP |
Civil Engr. | Ayres Associates |
Structural Engr. | Bloom Companies, LLC |
General Contractor | Terra Engineering |
Mechanical | 1901 Inc. |
Electrical | Forward Electric, Inc. |