DFD #14L2V
The project will construct a 3,500 SF addition to the existing potato building on the Lelah Starks Farm. The new addition will function as a potato grading and sorting area. The addition will be metal framed and sided with concrete foundations and flooring. A masonry fire separation wall will be constructed between the new and existing buildings. Three overhead doors will be provided for farm equipment access. The building is to be insulated and minimal heating will be provided. Electrical and plumbing work will be included to facilitate grading and sorting operations.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $394,000 |
Construction | $314,000 |
Design | $28,050 |
Mgt. | $13,800 |
Contingency | $31,400 |
Equipment | – |
Other Fees | $7,150 |
Funding Sources: | |
Agency Cash | $394,000 |
Timeline
A/E Selection | 02/2015 |
35% Design Report | 04/2015 – 02/2016 |
Construction Documents | 03/2016 – 10/2016 |
Bid Date | 01/2017 |
Rebid Date | 10/2017 |
Construction | 04/2018 – 08/2018 |
Substantial Completion | 08/2018 |
Occupancy | 09/2018 |
Key Stakeholders
Occupants | CALS |
User Reps | Doug Sabatke |
UW PM | Matt Collins |
DFD PM | Evan Quilling |
A/E | Jewell Associates Engineers |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Altmann Construction |
Plumbing | N/A |
Mechanical | N/A |
Fire Protection | N/A |
Electrical | Pieper Electric |
Area Data
GSF | 3,500 |
ASF | 3,342 |
Efficiency | 95.49% |
Construction $/GSF | $90 |