DFD #16B1C
This project will replace the existing sanitary sewer lift station in the lower level of the Limnology Building and replace the associated four-inch force main and the adjacent four-inch domestic water service to the building and the adjacent Water Science and Engineering Laboratory.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $115,000 |
Total Construction Costs | $733,000 |
Total Project Costs | $848,000 |
Funding Sources: | |
GFSB | $584,400 |
Agency Cash | $262,600 |
Timeline
A/E Selection | 03/2016 |
Design Report | 12/2017 |
Bid Date | 04/2019 |
Start Construction | 06/2019 |
Project Close-Out | 12/2019 |
Key Stakeholders
Occupants | UW Plumbing |
User Reps | Marcella Otter |
UW PM | Brandon Braithwaite |
DFDM PM | Kris Anderson |
A/E | Ayres Associates |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Terra Engineering |
Plumbing | TBD |
Mechanical | Hooper Corporation |
Fire Protection | TBD |
Electrical | TBD |