This project will design and construct a new 600+ stall parking garage in the existing Lot 62 parking lot to replace parking spaces lost from the expansion of the School of Veterinary Medicine addition and the new Meat Science and Animal Biologics Discovery Building.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $3,338,500 |
Total Construction Costs | $20,308,500 |
Total Project Costs | $23,647,000 |
Funding Sources: | |
Agency Cash | $10,635,800 |
GFSB | $13,011,200 |
Timeline
A/E Selection | 03/2017 |
Design Report | 04/2019 |
Bid Date | 07/2019 |
Start Construction | 09/2019 |
Substantial Completion | 12/2020 |
Key Stakeholders
Occupants | Transportation Services |
User Reps | Patrick Kass |
UW PM | Mike Zimmerman |
DFDM PM | Jake Ehmke |
A/E | Potter Lawson Inc. |
Structural Engr. | Kimley Horn |
General Contractor | JP Cullen |
Plumbing | Zimmerman |
Mechanical | 1901 |
Fire Protection | Automatic Fire Systems |
Electrical | Westphal+Company |
Area Data
GSF | 190,200 |
ASF | 180,690 |
Efficiency | 95.00% |
Construction $/GSF | $116 |
Total Project $/GSF | $124 |