MSN# 0520-1805
This project will remodel and add additional fume hoods to the 105 suite in the Materials Science & Engineering Building: remodel Room 105E as a research lab which requires the addition of four fume hoods, updated cabinetry, flooring, and supporting infrastructure; install an additional fume hood in Room 105D; and replace the existing, aging fume hood with a new model in Room 105C.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $138,000 |
| Total Construction Costs | $719,000 |
| Total Project Costs | $857,000 |
| Funding Sources: | |
| Gifts & Grants | $857,000 |
Timeline
| A/E Selection | 12/2018 |
| Design Report | 04/2019 |
| Bid Date | 08/2019 |
| Start Construction | 09/2019 |
| Substantial Completion | 02/2020 |
Key Stakeholders
| Occupants | College of Engineering |
| User Reps | Peter Nemmetz |
| UW PM | Dennis Rodenberg |
| DFDM PM | TBD |
| A/E | Continuum |
| Structural Engr. | TBD |
| General Contractor | TBD |
| Plumbing | TBD |
| Mechanical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
Area Data
| GSF | 1,401 |
| ASF | TBD |
| Efficiency | TBD |
| Construction $/GSF | $374 |
| Total Project $/GSF | TBD |