MSN #0040-1801
The project consisted of removing roughly 9,700 SY of existing turfgrass field, laser fine grading and laying bluegrass sod at the Division of Intercollegiate Athletics’ soccer game field located inside McClimon complex. This project has been substantially completed.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $39,000 |
Total Construction Costs | $311,000 |
Total Project Costs | $350,000 |
Funding Sources: | |
Gifts & Grants | $350,000 |
Timeline
A/E Selection | 12/2018 |
Design Report | 04/2019 |
Bid Date | 07/2019 |
Start Construction | 08/2019 |
Project Close-Out | 02/2020 |
Key Stakeholders
Occupants | Athletics |
User Reps | Barry Fox |
UW PM | Brandon Braithwaite |
DFDM PM | N/A |
A/E | Smithgroup |
Structural Engr. | N/A |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Fire Protection | N/A |
Area Data
GSF | TBD |
ASF | TBD |
Efficiency | TBD |
Construction $/GSF | TBD |
Total Project $/GSF | TBD |