MSN #0040-1601
To resurface the McClimon 400M outdoor track and adjacent field event areas; and surface the practice throw area and javelin runway.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $834,300 |
Construction | $726,700 |
Design | $37,400 |
Mgt. | $25,200 |
Contingency | $45,000 |
Equipment | – |
Other Fees | – |
Funding Sources: | |
Gift | $834,300 |
Timeline
A/E Selection | 08/2016 – 12/2016 |
35% Design Report | 01/2017 – 02/2017 |
Construction Documents | 02/2017 – 04/2017 |
Bid Date | 04/2017 |
Rebid Date | 06/2017 |
Construction | 06/2018 – 07/2018 |
Substantial Completion | 07/2018 |
Occupancy | 07/2018 |
Key Stakeholders
Occupants | Wisconsin Athletics |
User Reps | Barry Fox |
UW PM | Matt Collins |
DFD PM | N/A |
A/E | Rettler Associates |
Design Arch. | TBD |
Landscape Arch. | TBD |
Structural Engr. | TBD |
General Contractor | Beynon Sports |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |