16C1Y
This project remodels suite 206d in the Engineering Centers Building for a new facility recruit involved in Metal Organic Chemical Vapor Deposition (MOCVD) used in the manufacturing of computer chips. It will be an H5 hazardous occupancy with intensive equipment needs.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $756,000 |
Construction | $608,000 |
Design | $60,800 |
Mgt. | $27,000 |
Contingency | $60,800 |
Equipment | – |
Other Fees | – |
Funding Sources: | |
Gifts & Grants | $756,000 |
Timeline
A/E Selection | 04/2016 |
35% Design Report | 05/2016 – 07/2016 |
Construction Documents | 07/2016 – 08/2016 |
Bid Date | 12/2016 |
Construction | 02/2017 – 11/2017 |
Substantial Completion | 11/2017 |
Occupancy | 11/2017 |
Key Stakeholders
Occupants | College of Engineering |
User Reps | Sharon Devenish |
UW PM | Pete Heaslett |
DFD PM | Doug Schorr |
A/E | KEE Architects |
Design Arch. | N/A |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Miron Construction |
Plumbing | Hooper Corp. |
Mechanical | H&H |
Fire Protection | Ahern |
Electrical | Forward Electric |