MSN# 0450-1802
This project remodels space on the fourth floor of the Medical Sciences Center (MSC) building. Currently, the Chemistry Learning Center (CLC) is housed in the Daniels building on campus. The renovation of Daniels will begin in the Fall of 2020 and CLC will need to relocate prior to the start of that renovation. This project will create small flexible-use classrooms and office space for CLC.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $283,660 |
Total Construction Costs | $1,016,340 |
Total Project Costs | $1,300,000 |
Funding Sources: | |
Gifts & Grants | $1,300,000 |
Timeline
A/E Selection | 08/2018 |
Design Report | 02/2019 |
Bid Date | 08/2019 |
Start Construction | 09/2019 |
Substantial Completion | 04/2020 |
Key Stakeholders
Occupants | Chemistry Learning Center |
User Reps | Tony Jacob |
UW PM | Bo Muwahid |
DFDM PM | N/A |
A/E | Aro Ebele |
Structural Engr. | TBD |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 4,900 |
ASF | 4,600 |
Efficiency | 93.88% |
Construction $/GSF | $232 |
Total Project $/GSF | $265 |