DFD #17H2H
This project reconstructs and expands Lot 130 from 93 to 100 stalls and converts Lot 129 (28 stalls) into a vegetated area.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $147,400 |
| Total Construction Costs | $622,600 |
| Total Project Costs | $770,000 |
| Funding Sources: | |
| Cash | $770,000 |
Timeline
| A/E Selection | 10/2017 |
| Design Report | 09/2018 |
| Bid Date | 04/2019 |
| Start Construction | 07/2019 |
| Substantial Completion | 10/2019 |
Key Stakeholders
| Occupants | Transportation Services |
| User Reps | Patrick Kass |
| UW PM | Mike Zimmerman |
| DFDM PM | Ed Keasler |
| A/E | Oneida Engineering Sol. |
| Design Arch. | N/A |
| Landscape Arch. | GRAEF |
| Structural Engr. | N/A |
| General Contractor | Poblocki Paving Corp |
| Plumbing | N/A |
| Mechanical | N/A |
| Fire Protection | N/A |
| Electrical | Universal Power&Systems |
Area Data
| GSF | N/A |
| ASF | N/A |
| Efficiency | N/A |
| Construction $/GSF | N/A |
| Total Project $/GSF | N/A |