MSN #0526-1703
This project, located at the Primate Center, will upgrade electrical systems and install a backup generator. A new electrical vault will be built over the existing electrical vault on the north side of the building.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $162,000 |
| Total Construction Costs | $1,038,000 |
| Total Project Costs | $1,200,000 |
| Funding Sources: | |
| Gifts & Grants | $1,200,000 |
Timeline
| A/E Selection | 02/2018 |
| Design Report | 10/2018 |
| Bid Date | 12/2019 |
| Start Construction | 03/2020 |
| Substantial Completion | 07/2020 |
Key Stakeholders
| Occupants | Graduate School |
| User Reps | Bruce Pape |
| UW PM | Bo Muwahid |
| DFDM PM | N/A |
| A/E | Mead & Hunt |
| Design Arch. | Mead & Hunt |
| Landscape Arch. | N/A |
| Structural Engr. | Mead & Hunt |
| General Contractor | TBD |
| Plumbing | TBD |
| Mechanical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
Area Data
| GSF | 500 |
| ASF | TBD |
| Efficiency | TBD |
| Construction $/GSF | $2,266 |
| Total Project $/GSF | $2,400 |