MSN #0526-1703
This project, located at the Primate Center, will upgrade electrical systems and install a backup generator. A new electrical vault will be built over the existing electrical vault on the north side of the building.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $162,000 |
Total Construction Costs | $1,038,000 |
Total Project Costs | $1,200,000 |
Funding Sources: | |
Gifts & Grants | $1,200,000 |
Timeline
A/E Selection | 02/2018 |
Design Report | 10/2018 |
Bid Date | 12/2019 |
Start Construction | 03/2020 |
Substantial Completion | 07/2020 |
Key Stakeholders
Occupants | Graduate School |
User Reps | Bruce Pape |
UW PM | Bo Muwahid |
DFDM PM | N/A |
A/E | Mead & Hunt |
Design Arch. | Mead & Hunt |
Landscape Arch. | N/A |
Structural Engr. | Mead & Hunt |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 500 |
ASF | TBD |
Efficiency | TBD |
Construction $/GSF | $2,266 |
Total Project $/GSF | $2,400 |