The scope of work consists of replacement and construction of steam utilities along Dayton Street from Mills to Park Streets and primary electrical/signal communication utilities along Dayton Street from Charter to Park Street. Improvements include replacement of high-pressure steam, pumped condensate return, and compressed air piping. The City of Madison will also be upgrading water main, sewer, and storm sewer utilities.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $2,316,000 |
Total Construction Costs | $17,040,000 |
Total Project Costs | $22,760,000 |
Funding Sources: | |
GFSB | $11,306,000 |
PRSB | $4,182,000 |
Cash | $1,687,000 |
Timeline
A/E Selection | N/A |
Design Report | N/A |
Bid Date | 01/2019 |
Start Construction | 04/2019 |
Substantial Completion | 04/2020 |
Key Stakeholders
Occupants | FP&M/Physical Plant |
User Reps | Jeff Pollei |
UW PM | Brandon Braithwaite |
DFDM PM | Michael Hanson |
A/E | Affiliated Engineers, Inc |
Design Arch. | N/A |
Landscape Arch. | Ayres Associates |
Structural Engr. | Bloom Companies, LLC |
MEP Engr. | N/A |
General Contractor | Terra Engineering |
Plumbing | N/A |
Mechanical | Hooper Corporation |
Fire Protection | N/A |
Electrical | Forward Electric, Inc. |
Area Data
GSF | TBD |
ASF | TBD |
Efficiency | TBD |
Construction $/GSF | TBD |
Total Project $/GSF | TBD |