As the campus continues to expand its academic offerings and enrollment, it needs to increase housing opportunities for incoming freshmen and returning students. By providing space within residence halls focused on the incoming freshman class program-based experience, students seek housing on campus to enhance their academic and social experience. The project will provide a full renovation of the space and add a new central core tower that will consolidate five new elevators, key mechanical equipment, accessible resident entry, and resident life space. Construction will also add two floors on top of the existing ten-story structure, allowing for approximately 250 new resident bed spaces.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $9,631,000 |
Total Construction Costs | $69,180,000 |
Total Project Costs | $78,811,000 |
Funding Sources: | |
PR Cash | $19,703,000 |
PRSB | $59,108,000 |
Timeline
A/E Selection | 10/2014 |
Design Report | 08/2019 |
Bid Date | 05/2020 |
Start Construction | 07/2020 |
Substantial Completion | 08/2023 |
Key Stakeholders
Occupants | University Housing |
User Reps | Adam Rittel |
UW PM | Dennis Rodenberg |
DFDM PM | Wendy von Below |
A/E | UWRS |
Design Arch. | Steve Groth |
Landscape Arch. | Smithgroup |
Structural Engr. | OTIE |
MEP Engr. | IMEG |
General Contractor | TBD |
Plumbing | TBD |
Mechanical | TBD |
Fire Protection | TBD |
Electrical | TBD |
Area Data
GSF | 330,931 |
ASF | 219,196 |
Efficiency | 66.24% |
Construction $/GSF | 209 |
Total Project $/GSF | 238 |