MSN #0057-1701
This project will make some building modifications to accommodate the Terrestrial Reconnection Experiment (TREX). Modifications include remodeling of the space on the second floor above the Plasma Dynamo Experiment (MPDX) to be used for assembly and storage of TREX equipment. An opening in the existing second-floor structure will be created to allow the TREX assembled components to be lowered into the MPDX. A crane will need to be hung from the existing third-floor structure, which will be used to insert the TREX assembled components into the MPDX. There will also be various alterations of some support spaces, as well as some MEP upgrades.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $65,995 |
Total Construction Costs | $497,005 |
Total Project Costs | $563,000 |
Funding Sources: | |
Gifts & Grants | $563,000 |
Timeline
A/E Selection | 06/2017 |
Design Report | 02/2018 |
Bid Date | 06/2018 |
Start Construction | 07/2018 |
Project Close-Out | 03/2019 |
Key Stakeholders
Occupants | Physics Department |
User Reps | John Wallace |
UW PM | Bo Muwahid |
DFDM PM | N/A |
A/E | KEE Architecture |
Design Arch. | KEE Architecture |
Landscape Arch. | N/A |
Structural Engr. | RA Smith National, Inc. |
General Contractor | Advanced Building Corp. |
Plumbing | UW DDC |
Mechanical | Prime Mechanical |
Fire Protection | Hooper Corp. |
Electrical | Electric Construction Inc. |
Area Data
GSF | 3,000 |
ASF | 2,900 |
Efficiency | 96.67% |
Construction $/GSF | $166 |
Total Project $/GSF | $22 |