DFD# 18A2A
This project replaces damaged clay tile roofing and associated roofing components. Project work includes complete removal and disposal of damaged clay tile roofing system down to the structural deck; removal, replacement and re-use (where applicable) of metal gutter and fascia; and installation of the new roofing system and associated components.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total Soft Costs | $173,900 |
| Total Construction Costs | TBD |
| Total Project Costs | $2,766,000 |
| Funding Sources: | |
| Gifts & Grants | TBD |
| AGFO | $173,900 |
Timeline
| A/E Selection | 03/2018 |
| Design Report | TBD |
| Bid Date | 01/2020 |
| Start Construction | 04/2020 |
| Project Close-Out | 10/2020 |
Key Stakeholders
| Occupants | UW Housing |
| User Reps | Jeff Keating |
| UW PM | Bo Muwahid |
| DFDM PM | Evan Quilling |
| A/E | Assemblage Architects |
| Structural Engr. | TBD |
| General Contractor | TBD |
| Plumbing | TBD |
| Mechanical | TBD |
| Fire Protection | TBD |
| Electrical | TBD |
Area Data
| GSF | TBD |
| ASF | TBD |
| Efficiency | TBD |
| Construction $/GSF | TBD |
| Total Project $/GSF | TBD |