MSN #0423-1701
This project includes demoltion of some storage area within one of the agricultural buldings on the West Madison ARS. In place of the demolished storage area, two coolers will be built to be used as seed storage. Their old facilites were torn down to make way for the new Meat Science building.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $500,000 |
Construction | $406,500 |
Design | $31,000 |
Contingency | $36,500 |
Equipment | $10,000 |
Other Fees | $16,000 |
Funding Sources: | |
Gifts & Grants | $500,000 |
Timeline
A/E Selection | 01/2018 |
25% Design Report | 03/2018 |
Construction Documents | 04/2018 |
Bid Date | 4/2018 – 5/2018 |
Construction | 07/2018 – 09/2018 |
Substantial Completion | 09/2018 |
Occupancy | 10/2018 |
Key Stakeholders
Occupants | CALS |
User Reps | Doug Sabatke |
UW PM | Bo Muwahid |
A/E | BWZ |
Design Arch. | BWZ |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Advanced Building Corp. |
Plumbing | N/A |
Mechanical | General Heating & AC |
Fire Protection | N/A |
Electrical | Westphal |