The project will renovate approximately 11,000 ASF / 13,850 GSF of floors B1, 1 and 2 of WIMR to accommodate up-to-date equipment, in vivo laboratory science, and greater office density. There are several distinct focuses of this project, each having different end users and unique considerations. Each of these areas is anticipated to be designed and built concurrently, with work being bid and executed as one bid package. The design of each requires modifications to Architectural and MEP systems, within operational scientific laboratory and clinical settings.
This is an accordion element with a series of buttons that open and close related content panels.
BUDGET
Total Soft Costs | $411,155 |
Total Construction Costs | $1,202,945 |
Total Project Costs | $1,614,100 |
Funding Source: | |
Gifts & Grants | $1,614,100 |
TIMELINE
A/E Selection | 04/2017 |
Design Report | 5/2017 – 8/2017 |
Bid Date | 12/2017 |
Construction | 01/2018 |
Substantial Completion | 09/2018 |
KEY STAKEHOLDERS
Occupants | SMPH |
User Reps | Jess Hisel |
UW PM | Rex Loker |
DFDM PM | N/A |
A/E | Zimmerman Architects |
Design Arch. | Scott Justus |
Landscape Arch. | N/A |
Structural Engr. | N/A |
General Contractor | Miron Constructions |
Plumbing | IBC |
Mechanical | Affiliated Engineers |
Fire Protection | IBC |
Electrical | Affiliated Engineers |
AREA DATA
GSF | 13,850 |
ASF | 11,000 |
Efficiency | 79.42% |
Construction $/GSF | $87 |
Total Project $/GSF | $117 |