Witte Hall’s core, first floor, and basement areas will be renovated and expanded to accommodate four new elevators, common space (floor lounge, study space, and kitchenette), and bathrooms. HVAC systems will be replaced/upgraded by adding individual heat controls in rooms and air conditioning throughout the halls. Windows will be replaced and resident rooms, hallways, and stairwells will be upgraded. There will be finish upgrades throughout. Construction began fall of 2017. Occupancy at the start of Fall 2019 is expected.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total Soft Costs | $5,466,460 |
Total Construction Costs | $47,330,540 |
Total Project Costs | $52,797,000 |
Funding Sources: | |
Program Revenue | $52,797,000 |
Timeline
A/E Selection | 12/2014 |
Design Report | 09/2015 |
Bid Date | 12/2016 |
Start Construction | 03/2017 |
Substantial Completion | 08/2019 |
Key Stakeholders
Occupants | University Housing |
User Reps | Mike Kinderman |
Adam Rittel | |
UW PM | Bo Muwahid |
DFDM PM | Wendy von Below |
A/E | UWRS |
Design Arch. | Steve Groth |
Landscape Arch. | SmithGroupJJR |
Structural Engr. | OTIE |
MEP Engr. | IMEG |
General Contractor | CD Smith |
Plumbing | Monona |
Mechanical | H&H Industries |
Fire Protection | H.J. Pertzborn |
Electrical | H&H Electric |
Area Data
GSF | 287,324 |
ASF | 174,358 |
Efficiency | 60.68% |
Construction $/GSF | $165 |
Total Project $/GSF | $184 |