This 146,154 GSF/121,795 ASF project is provided in three phases separated by two football seasons. It consists of preplanning for the Athletic Performance Center for football locker rooms, sports medicine and strength and conditioning. This $86,165,000 project includes a remodel of the 2nd floor East stadium and the lower level of the McClain Center, an expansion of the Fetzer Center, and a tunnel connection to Camp Randall Stadium. The Performance Center Plaza portion of the Badger Way Landscape upgrades will include an exterior plaza with paving and landscaping along Badger Way Path from Breese Terrace to the Camp Randall Arch as well as completion of the Engineering Mall. Phase I construction began December 2011 and was substantially complete in October 2012. Phase II construction began June 2012 and was substantially complete in December 2012. Phase III construction began November 2012.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $86,165,000 |
Construction | $71,316,000 |
A/E & Other Fees | $5,499,000 |
FF&E | $2,600,000 |
Contingency | $3,850,000 |
DFD Fee | $2,800,000 |
Haz Mat | $100,000 |
Sources | |
PRSB | $49,200,000 |
Gifts | $36,956,000 |
Timeline
A/E Selection | 11/2010 |
Planning | 12/2010 |
Programming | 01/2011 – 04/2011 |
10% Concept Report | 04/2011 |
35% Design Report | 06/2011 |
Construction Documents | 10/2011 |
Bid Date | 11/2011 |
Construction | 12/2011 – 12/2013 |
Substantial Completion | 12/2013 |
Occupancy | 01/2014 |
Key Stakeholders
Occupants | Athletic Department |
User Reps | Jason King |
UW PM | Ann Hayes |
DFD PM | Tim Luttrell |
A/E | Berners-Schober Associates |
Design Arch. | VOA Associates, Inc. |
Landscape Arch. | SmithGroup JJR |
Structural Engr. | Arnold & O’Sheridan Inc. |
CMAR | J.P. Cullen & Sons, Inc. |
Plumbing | Monona, Hooper |
Mechanical | North American, General |
Heating & Air Cond. | |
Fire Protection | Monona, H.J. Pertzborn |
Electrical | Nickles Electric, Inc. |
Area Data
GSF | 146,154 |
ASF | 121,795 |
Efficiency | 83.33% |
Construction $/GSF | $487.95 |
Total Project $/GSF | $589.55 |
- LEED Silver
- Sustainable Sites
- Energy & Atmosphere
- Materials & Resources
- Indoor Environmental Quality
- Quarterly Report Project PDF
There are two separate certified LEED projects within the Student Athlete Performance Center. The Camp Randall North Addition (Phase III) achieved LEED New Construction, and the McClain Center (Phase II) achieved LEED Commercial Interiors for the remodeling work. Both the Camp Randall North Addition (Phase III) and the McClain Center achieved LEED Silver certification.
Both facilities are within a quarter mile of 11 bus stops, alternative transportation.
Over 575,000 kWh of wind power, a renewable energy source, will be purchased and used in the operations of the McClain Lower Level each year.
Over 20% of the materials used in the McClain remodeling were from local sources which helps reduce the amount of fossil fuels required to transport materials. The stone show in the picture to the left was extracted in Fond du Lac, WI and then processed & manufactured in Chilton, WI.
Low-VOC and zero-VOC materials were used throughout the remodeling of the McClain Center.