MSN #0055-1703
This project takes existing student office space and converts it into two laboratories for a new faculty member. The labs will implement a dedicated air handler as the two new labs will have strict temperature and relative humidity controls.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
| Total | $715,000 |
| Construction | $378,000 |
| Design | $68,000 |
| Contingency | $255,000 |
| Equipment | |
| Other Fees | $14,000 |
| Funding Sources: | |
| Gifts & Grants | $715,000 |
Timeline
| A/E Selection | 08/2017 |
| 25% Design Report | 09/2017 – 11/2017 |
| Construction Documents | 12/2017 – 03/2018 |
| Bid Date | 04/2018 – 05/2018 |
| Construction | 6/1/2018 – 10/2018 |
| Substantial Completion | 10/2018 |
| Occupancy | 11/2018 |
Key Stakeholders
| Occupants | Physics Department |
| User Reps | Aimee Lefkow |
| UW PM | Bo Muwahid |
| DFD PM | N/A |
| A/E | Assemblage Architects |
| Design Arch. | Assemblage Architects |
| Landscape Arch. | N/A |
| Structural Engr. | N/A |
| General Contractor | Advanced Building Corp. |
| Plumbing | Hooper Corp. |
| Mechanical | H&H Indsutries |
| Fire Protection | N/A |
| Electrical | Universal Power Systems |
Area Data
| GSF | 1,300 |
| ASF | 1,200 |
| Efficiency | 92.31% |
| Construction $/GSF | $402 |