DFD #14I1O
This project reconfigures two gravel parking lots into a single lot, provides various site improvements for storm water drainage and operating efficiencies, and provides a new 40’x80′ pre-engineered wood framed with metal siding equipment shed. Electrical power and lighting will be supplied and served from an adjacent campus building.
This is an accordion element with a series of buttons that open and close related content panels.
Budget
Total | $450,300 |
Construction | $258,200 |
Design | $34,600 |
Mgt. | $15,800 |
Contingency | $35,800 |
Equipment | – |
Other Fees | $5,900 |
Funding Sources | |
PR Funds | $450,300 |
Timeline
A/E Selection | 12/2014 |
35% Design Report | 05/2015 – 11/2015 |
Construction Documents | 12/2015 – 02/2016 |
Bid Date | 04/2016 |
Rebid Date | 12/2016 |
Construction | 04/2017 – 07/2017 |
Substantial Completion | 07/2017 |
Occupancy | 09/2017 |
Key Stakeholders
Occupants | UW Housing |
User Reps | Evan Quilling |
UW PM | Bo Muwahid |
DFD PM | Jake Ehmke |
A/E | Kontext Architects |
Design Arch. | Kontext Architects |
Civil Engr. | Edge Consulting |
Structural Engr. | N/A |
General Contractor | N/A |
Plumbing | N/A |
Mechanical | N/A |
Fire Protection | N/A |
Electrical | N/A |
Area Data
GSF | 3,200 |
ASF | 3,120 |
Efficiency | 98.00%% |
Construction $/GSF | $80 |
Total Project $/GSF | $140 |